Project Management Terminology
Critical Path. The sequence of activities that represents the longest path through a project, which determines the shortest possible duration.
Total Float. The amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint.
Common Acronyms
EV (english) : Earned Value
If you are managing projects here are 6 good reasons to obtain your certification as Project Management Professional, PMP.
Discover how you can accomplish your PMP in 6 months as a very busy person.
Question to a Project Management Professional
Question | Select the best option |
In the following list, which inputs is not an input of the process “Close Project or Phase”? |
|
Answer & Explanation
Right answer |
|
Explanation : These inputs are inputs of the process “Close Project or Phase” except work performance information. |