Project Management Terminology
Performance Measurement Baseline (PMB). Integrated scope, schedule, and cost baselines used for comparison to manage, measure, and control project execution.
Procurement Strategy. The approach by the buyer to determine the project delivery method and the type of legally binding agreement(s) that should be used to deliver the desired results.
Common Acronyms
COQ (english) : Cost of Quality
If you are managing projects here are 6 good reasons to obtain your certification as Project Management Professional, PMP.
Discover how you can accomplish your PMP in 6 months as a very busy person.
Question to a Project Management Professional
Question | Select the best option |
You are taking over a project that is about 50% complete. The former project manager tells you that there were a lot of changes required by external stakeholders. Only few of them have been implemented so far. Which of the changes are documented? |
|
Answer & Explanation
Right answer |
|
Explanation : All changes should be formally documented in writing and any verbally discussed, but undocumented, changes should not be processed or implemented. Although changes may be initiated verbally, they should always be recorded in written form and entered into the change management and/or configuration management system. |