Project Management Terminology

Perform Integrated Change Control. The process of reviewing all change requests; approving changes and managing changes to deliverables, organizational process assets, project documents, and the project management plan; and communicating the decisions.

Risk Management Plan. A component of the project, program, or portfolio management plan that describes how risk management activities will be structured and performed.

Common Acronyms

SOW (english) : Statement of Work

If you are managing projects here are 6 good reasons to obtain your certification as Project Management Professional, PMP.

Discover how you can accomplish your PMP in 6 months as a very busy person.

Question to a Project Management Professional

Question Select the best option
What is the least source of conflict?
  1. Personality.
  2. Technical opinions.
  3. Project priorities.
  4. Schedule.
Answer & Explanation
Right answer
  1. Personality.
  2. Technical opinions.
  3. Project priorities.
  4. Schedule.

Explanation: It is always a surprise to discover that personality is rarely the source of conflicts. On the other hand, personality may increase or decrease the sensitivity of a conflict.

See also PMBOK® Guide – Sixth Edition: Sec. 9.4.2.4.

Why are more than 790.000 executives around the globe certified as PMP?

  • Reason 1: Better opportunities for attractive positions
  • Reason 2: Prospects of above average income
  • Reason 3: Personal development
  • Reason 4: Knowledge and ability up to date
  • Reason 5: Competences in the international context
  • Reason 6: Comprehensive operational capability

Discover how you can accomplish your PMP in 6 months as a very busy person.

>>> 4 to 6 months with individual telecoaching in German – English – French – Spanish>>>