Matrix Diagrams. A quality management and control tool used to perform data analysis within the organizational structure created in the matrix. The matrix diagram seeks to show the strength of relationships between factors, causes, and objectives that exist between the rows and columns that form the matrix.
Common Acronyms
CPFF (english) : Cost-Plus-Fixed-Fee
If you are managing projects here are 6 good reasons to obtain your certification as Project Management Professional, PMP.
Question to a Project Management Professional
Question | Select the best option |
A project manager is discussing with an expert how long it would take for paint to completely dry before starting the decoration of walls. The project manager is most likely in a process of: |
|
Answer & Explanation
Right answer |
|
Explanation : The delay between painting and the decoration of walls is a lag that directs a delay in the successor activity. Lags and leads are determined during Sequence Activities in order to accurately define logical relationships between activities. Leads and lags are documented in the activity attributes and serve later on as inputs to Develop Schedule. See also PMBOK® Guide – Sixth Edition: Chap. 6, Sec. 6.5.2.2 Schedule network analysis. |